Курсовая работа: Сетевое планирование и управление в менеджменте
Расчет позднего времени наступления события.
Tп0 = 0
Tп1 (1-6-11-13-14) = 80-(2+30+20+10)=18
Tп2 (2-7-11-13-14) = 80-(0+20+20+10)=30
Tп3 (3-7-11-13-14) = 80-(2+20+20+10)=28
Tп4 (4-8-3-7-11-13-14) = 80-(4,3+0+2+20+20+10)=23,7
Tп5 (5-10-13-14) = 80-(4+4+10)=62
Tп6 (6-11-13-14) = 80-(30+20+10)=20
Tп7 (7-11-13-14) = 80-(20+20+10)=30
Tп8 (8-3-7-11-13-14) = 80-(0+2+20+20+10)=28
Tп9 = 80-(4+4)=72
Tп10 = 80-(4+10)=66
Tп11 = 80-(20+10)=50
Tп12 = 80-4=76
Tп13 = 80-10=70
Tп14 = 80-0=80
Определение резервов времени работ.
R0-1 = Tп1 – Tр0 – t0-1 = 18-0-4,3=13,7
R0-2 = Tп2 – Tр0 – t0-2 = 30-0-30=0
R0-3 = Tп3 – Tр0 – t0-3 = 28-0-4=24
R0-4 = Tп4 – Tр0 – t0-4 = 23,7-0-3,5=20,2
R1-5 = Tп5 – Tр1 – t1-5 = 62-4,3-4=53,7
R1-6 = Tп6 – Tр1 – t1-6 = 20-4,3-2=13,7
R2-7 = Tп7 – Tр2 – t2-7 = 30-30-0=0
R3-7 = Tп7 – Tр3 – t3-7 = 30-4-2=24
R4-8 = Tп8 – Tр4 – t4-8 = 28-3,5-4,3=20,2
R4-9 = Tп9 – Tр4 – t4-9 = 72-3,5-3=65,5